Scrum tales - Part 9 - The Five Whys

When the sprint ends we expect all committed goals to succeed which unfortunately is not always the case. Scrum teams must meet to discuss what went wrong and to discover the flaws in the process vs. just toss the blame around

Scrum teams meet to conduct a Sprint retrospective meeting with the main purpose to identify and analyze the issues in the Sprint process and to figure out how to fix them in the future sprints. Sprint is an iterative process and no matter what goals fail there is always a reason why they failed and it is not due to one team or one person's fault but due to a flaw in a process; this underlying flaw is what teams almost always fail to identify and skip finding a way to resolve it in the future sprints

Let's reflect on what great companies already did before us and use it to our advantage - specifically the Five Whys lean manufacturing technique will help us explore cause and effect relationships underlying specific issues we encounter and to finally get to the root cause of a problem or in our case a failed sprint goal

How do the Five Whys work? The team meets to discuss an issue and iteratively asks five times "Why?" or more specifically "Why did the process fail?" followed by determining a Proportional investment how to solve the issue going forward. Best to illustrate this with an example applicable to Scrum and the everyday goals we have:

Developer team sprinted and Product backlog item saying "Get new product maintenance version approved for production" failed. During the Scrum team retrospective meeting, the following questions should be asked and answered:
   1) First Why
Q: Why wasn't the product approved for production?
A: Not all High priority bugs were fixed in time to get the approval
Proportional investment: This is not a preferred solution, but if it comes down to a time crunch, you will roll up your sleeves for a weekend and catch up

   2) Second Why
Q: Why weren't all High priority bugs fixed?
A: New bugs were discovered during the unplanned third static testing round
Proportional investment: You will always assume there will be maximum number of static testing rounds when planning a new Sprint and never raise everyone's expectations by committing to releasing the product if the goal is too risky

   3) Third Why
Q: Why did the product go into three static testing rounds?
A: The product was of lower quality than expected even though it is a maintenance release
Proportional investment: You will always plan ahead for better internal self-testing before sending a new build to a static test round to catch and fix the low hanging fruit before it goes over to QA and results in unexpected new bugs

   4) Fourth Why
Q: Why was the product of lower quality than expected for a maintenance release?
A: Some of the engine code was rewritten in between test rounds in order to fix a specific bug that a customer requested to be patched
Proportional investment: Always first raise a hand when you see large code changes are needed and review with Product owner vs. hacking away at previously tested code and in the middle of product testing, no matter if the Almighty asked for the patch in person

   5) Fifth Why
Q: Why was the engine code rewritten between during final product testing phase?
A: We have to fix ASAP all bugs forwarded over by Support team that customers need fixed, no matter if we're in final testing phase or not, we have team performance goal to achieve
Proportional investment: No, you don't; this means our system is flawed and the product will be delayed meaning all customers will have to wait or risk getting lower quality build for one specific bug fix. Let's make a rule not to patch anything during product testing phase and instead do it immediately after the release to production if deemed necessary

To help out with asking and answering the Whys, I will volunteer to be the Why Master for all Scrum teams meaning you need to invite me in all Scrum retrospective meetings if your sprint goals failed to quickly discuss how to improve our processes and prevent future sprint goal failures